Free Evangelical School Dresden - Digital Lean Construction Transformation

From post-its to lcmd: 30 million euro school project completed on schedule

Project Stats

Project duration

2023 - 2025

Project volume

30 Mio.€

Industry

Real Estate

Area

Commercial Construction

Project overview

Builder: Free Evangelical School Dresden

General contractor: OTTO QUAST Bau AG‍

FES Dresden is expanding its campus with a modern grammar school for 600 students. The project comprises a sports hall (already completed) and a three-part school building with canteen, auditorium and classrooms. ‍

Completion of the entire project, including outdoor facilities: December 31, 2025

Project data

Building:

  • Sports hall: 1,480 m², 101 precast concrete elements
  • School building: 3 buildings, multi-storey
  • Capacity: 600 students

lcmd setup:

  • 10 active users
  • 2+ years project duration
  • Weekly meetings
No items found.

Challenges & solutions

Delayed building permit

Agile replanning with lcmd enabled flexible adjustment of cycle planning‍

Complex ground floor Separate pull plan for cantea/auditorium area in case of building technology delays‍

Mixed online/face-to-face meetings

lcmd visualization works seamlessly in both formats

lcmd in use

After 6 years of experience with analog Last Planner, project manager Michael Boss used lcmd for the first time from the planning phase to completion.

Core Features:

  • Cycle planning: Partial structuring of buildings (A, B, C), timed areas by level
  • Collaboration: Weekly meetings with 8-10 trades, 6-week exports as minutes
  • Remote control: Project management from Siegen for construction site in Dresden
  • Monitoring: Dashboard with progress bar and evaluation of key figures

I see the biggest advantage in the fact that I can simply immediately overview the overall process plan in all possible scaling variants and filter variants without having to work with paper printouts and complex post-it wall panels. The online availability and the ability to use and adapt the plan in video conferences also make my work much easier.

Michael Boss

Project Manager | OTTO QUAST Fertigbau GmbH

Project success

- Completion of the entire project, including outdoor facilities, by December 31, 2025

- Completion on schedule despite delays in obtaining building permits

- High level of acceptance among all project participants‍‍‍

Outlook

The successful FES project serves as a pilot for the company-wide implementation of lcmd at OTTO QUAST - the structural engineering areas and the Dresden branch are planned.